www.FranzosenbuschHeritageProject.org                     Home


District 92 ½ New Buildings and Additions -- 1929 - 1949
Compiled by Charles N. Field, 1949

Prior to the erection of any buildings, classes were held in residences at 1623 Newcastle Avenue and at a location in the 700 block on Newcastle Avenue. Discussion on school buildings t be located at the Hull and Gladstone site and the Canterbury and Suffolk site referred to them as the Gladstone and the South Side or Canterbury School.

The original estimated cost of these two proposed two-room buildings totaled $30,000. The contract with Architect W. S. Holmes on July 15, 1929 stipulated the total cost was not to exceed $30,000 and when the bids were received November 30, 1929 on the Gladstone School from Meyer Stils and Company for 26,006 minus plumbing, heating and electrical, and from Guy McClintock and Company for $24,730 minus heating, plumbing and electrical, the drawings were turned back to the architect and his contract canceled.

January 13, 1930 contracted with Architect C. W. Lampe for drawings and specifications for North Side School at a fee of $450.00.

March 10, 1930

Contract awarded for North Side School to Schmidt Brothers for $18,680. Residents cast votes to name building the Grant N. Britten School. Minutes do not show how or where votes was taken or that Board named school by a resolution.

Photograph by Charles Field.

September 8,1930

Bids accepted for South Side School as follows:

A. C. Larsen and Son

$23,660

A. S. Caron and Son

$24,203

Schmidt Brothers

$24,000

October 14, 1930

Minutes show that by popular "vote" (no indication as to how or where vote was taken) it was requested that South Side School be known as the George F. Nixon School. School so named by motion of the Board.

Minutes show contract was awarded to lowest bidder, Schmidt Brothers, for $21,260.Sounds as if bid was negotiated.

June 27, 1935

Made application to Federal government for a grant to build an addition to the Nixon School. P. W. A. turned down application #1256 per minutes May 15, 1936. George Sass was the school attorney.

July 18, 1935

Mr. Heath retained as Architectural Advisor to prepare plans and get an estimate for an addition to the Nixon School.

November 12, 1936

Hired architect W. Walker to develop plans for Nixon Addition to be presented with application to the Federal grant.

June 25, 1941

Meeting with Midland Development Company relative to acquiring a site in Highridge subdivision. It was indicated site could be acquired at cost.

August 13, 1941

Midland Development Company offered ten lots for $4800 with a 90-day option.

September 28, 1941

Midland Development Company agree to give a one-year option to purchase the above ten lots at southeast corner of Canterbury and Haas. Deed to restrict for only school use. In exchange, school district agreed pick up children in Highridge with school bus.

November 15, 1941

Met with Architect Willard Walker to discuss plans for a two-room, with basement and gymnasium, addition to the Nixon School due to possibility that WPA might contribute 65% of the cost.

December 10, 1941

Made Midland's letter of October 28, 1941 a part of the minutes.

  • School district to decided by January 1, 1943 if it will erect a school by January 1, 1945 on 12 lots between Fielding and Canterbury on Hass.
  • School district to pay $1,000 by January 1, 1943.
  • Suggested vacation of Haas Avenue to provide area 600 feet by 800 feet.
  • School to pay proportionate share of sewer between Canterbury and Fielding Streets.

January 14, 1942

Application filed with Federal Reserve Improvement Department for an addition to the Nixon School.

May 13, 1942

Architect Charles A. Kristen presented plans and an estimate of $3500 for a one-room addition to the Britten School.

July 31, 1942

First contract for use of basement of Lutheran Church for classes (See supplement 1/13/43) for $860.00.

October 14, 1942

Decided to retain Louis Ancel as attorney to investigate every possibility of securing aid to erect additional facilities because of 250 new home project north of 12th Street.

December 20, 1942

Attorney Ancel reported administrators of the Lanham Act could approve school aid in areas having war housing. Forms were submitted for completion of application.

June 5, 1943

Application to WPB being prepared by Architect Kristen for priority assistance to build a two-room addition to the Britten School.

July 14, 1943

WPB gave a AA4 priority rating on proposed two-room addition to Britten School estimated to cost $5,000. As on $2,500 in the Building Fund, proposal made to Sudler Construction to erect addition at cost and permit school district to pay the excess cost of $2,500 at rate of $500 every six months.

August 11, 1943

Sudler Construction Company, a developer in Westchester, turn down the proposition of financing the addition to the Britten School.

September 8, 1943

Attorney Ancel was directed to file an application for government assist to add two rooms to each of the schools at an estimated cost of $20,000.

October 13, 1943

Attorney Ancel reported no hope for Federal assistance on additions to schools as District was not bonded to its legal limit.

November 10, 1943

Messrs. Rosen and Goldstein of Power Construction Company made a tentative bid of $7,500 for a two-room addition to Britten, exclusive of heating and lighting.

November 19, 1943

Board requested representatives of Home Owners, P. T. A., etc., to consider advisability of building the two-room addition to the Britten School, explaining that it would be necessary to sell tax anticipation warrants against the 1943 and 1944 building fund levies. John Massie (Home Owners) moved, and Charles Field (PTA) seconded that the group present were in favor of this proposed addition.

December 8, 1943

Township School Treasurer Albert C. Roos agreed to transfer $5,000 from the Education Fund as a loan to the Building Fund to apply to this project.

December 22, 1943

Signed contract with Power Construction Company for $8,261 for this addition.

January 22, 1944

Contract awarded to Cicero Sheet Metal for $860 to change present heating plant to also heat new addition. Approved an extra $442 to plaster walls and ceilings of new addition as Village Organization had agreed to raise fund to cover this extra.

April 12, 1944

Check received from School Benefit Fund for $1,045.02 to take care of plastering the Britten School.

April 11, 1945

Decided to hire architect to design a four-room addition to the Nixon as District qualified for Federal building assistance under the Lanham Act.

June 13, 1945

Lanham Act application for addition to the Nixon School was approved in the Chicago office and sent to Washington for final approval.

July 5, 1945

The Federal Works Agency in Washington approved a grant of $49,650 for the Nixon addition.

August 8, 1945

Approved purchase of 12 lots on Haas Avenue from the Midland Development Company as per option in their letter of October 8, 1941. Attorney Ancel reported this was refused by Midland Development Company as option had terminated.

September 12, 1945

Authorization grant under Lanham Act canceled by the government because of the termination of hostilities with Japan. The Lanham Act was a war emergency act.

October 10, 1945

Investigation started on possibility of a loan from RPC to finance an addition.

Search started to locate other village facilities suitable for classroom use.

Investigation started to determine cost of portable school buildings.

Report of joint meeting with Village Board on October 9, 1945, relative to School District obtaining a deed from Midland Development company for approximately seven acres several blocks south of Canterbury Street in line with Highridge Parkway.

January 15, 1946

Perkins and Will, Architects, instructed to prepare plans for a two-room addition to Nixon School to cost $20,000.

February 13, 1946

Approved Perkins and Will plans and specifications for a four-room addition to the Nixon School.

Let contract to cinder an "L"-shaped alley at north end of Britten School site and to block existing alley along side of building. Prior to building across the old alley it will be necessary to dedicate new alley to the Village and have them vacate old alley.

At a joint meeting of School and Village Boards Midland Development Company agreed to provide an alternate school site on Canterbury Street between Evers Avenue and Highridge Parkway, with the understanding if the school did not build on the alternate site before the acreage was developed the alternate site would be relinquished and the original site would be deeded to the District.

May 15, 1946

Bids received for a four-room addition to Nixon School:

Blauner Construction Company

$54,440 base bid

Power Construction Company

$50,514 base bid

Coath and Goss

$46,845 base bid

As bids were in excess of the $20,000 authorized in bonds plus funds on hand, meeting was adjourned until May 23, 1946 to investigate cost of temporary structure, possibility of selling more bonds and the possibility of lowering costs by change in plans or specifications.

May 23, 1946

All bids were rejected and Perkins and will were directed to work with Power Construction Company on their suggestions for cost reduction.

May 28, 1946

Received bid of $2300 for a 24 feet by 60 foot Quonset Hut plus foundation, floor, heat and light to cost $5000 to $6000.

June 6, 1946

Mr. Edgar Romilly of the Forest Preserve District, a former School Board member, advised that a CCC barracks at Lemont would e available "as is" without cost.

June 27, 1946

Agreed to accept CCC barracks "as is" from Forest Preserve and to move building to Westchester to serve as three classrooms to be known as Romilly Hall. Power Construction Company submitted an estimate of $1823 to build foundation for this building.

July 10, 1946

Village granted approval for erection of Romilly Hall and contract awarded to Claude Schultes for $1200 to move barracks to site.

July 19, 1946

Accepted bid of $2196 from Power Construction Company for revised foundation and also a bid for other work to complete Romilly Hall on a cost plus 10% plus 10% basis.

Bid received from Power Construction Company for four-room addition to Nixon School, excluding plastering, for $36,490.

August 27, 1946

Accepted bid of Power Construction Company for Nixon Addition, including plastering, of $38,703 subject to extras required by Village change in plans. Passed resolution to issue the $40,000 of 3% bonds that were authorized.

September 11, 1946

$217.21 supplement bid of Power Construction Company brought contract to $38,920.21.

November 13, 1946

Romilly Hall to open for classes November 18, 1946. Approved hiring of a night janitor at $100 per month to handle this building and Nixon School.

December 11, 1946

Dedication of Romilly Hall to be held at PTA meeting in building on January 9, 1947.

January 8, 1947

Final payments brought total for Romilly Hall to $16,122.58.

April 9, 1947

Power Construction Company bid for bus garage for Britten site:

  • Double, $7556
  • Single, $5376

Accepted bid for double garage.

May 15, 1957

Village Trustees hold up permit to build bus garage on Britten site because of opposition of residents in that area. School Board decided to postpone erection of garage.

September 29, 1947

Board accepted from the Power Construction Company the completed four-room addition to Nixon School:

Contract price

$40,221.40

Louis Ancel - legal fee

500.00

Perkins and Will - architect

3,280.22

Extras by School Board

3,720.00

 

=======

Total

$47,721.62

It was noted that the cost of Romilly Hall completed the previous year was $16,122.58.

November 7, 1947

Awarded contract to Power Construction Company for $8,067to build a two-bus garage on the northwest corner of Kent and Norfolk, Nixon site.

November 20, 1947

Authorized purchase and laying of rubber tile on floors of upper classrooms in Nixon addition.

December 19, 1947

Mr. Louis N. Balluf, architect , retained to prepare plans and specifications for a classroom and auditorium addition to Nixon School.

February 13, 1948

Power Construction Company submitted an estimate on Mr. Balluf’s rough drawings of $170,000 for the classrooms and $80,000 for the auditorium. Attorney Ancel believed necessary bonds could be sold at 3-3 ¾ %. Previous Board members present, after considering the costs and the need, recommend that the Board should proceed with this project. Board approved resolution calling for a special election on March 13, 1948 to ask approval for a $275,000 bond issue and approval to build the proposed addition to the Nixon School.

May 20, 1948

Final payment of $3166 on bus garage to Power Construction Company.

May 28, 1948

Received bids for Nixon Addition -- five classrooms, auditorium/gymnasium, office, health room, kitchen, four toilet rooms, boiler room, shower room, drying room, two locker room and storage room.

Contractor

Base bid

Axel E. Johnson

$235,700

Kay Construction

$331,558

Power Construction

$239,000

John Traff

$249,400

No decision made on bids as Architect Balluff was requested to get information on the bidders.

June 3, 1948

Architect Balluff reported on his investigation of the various bidders. Letter from Power Construction Company explaining their bid caused the Board to direct a letter to all bona fide bidders advising the contract would be negotiated on certain detailed specifications and factors, and requested final bids by June 15, 1948.

June 15, 1948

Negotiated bids received on the original base, plus extras for face brick, etc.

Contractor

Final bid

Axel E. Johnson

$240,000

John Traff

$245,000

Power Construction

$237,756

After careful consideration of each contractor’s reputation for quality work, time each gave for expected completion and report of Board members’ inspections of schools each contractor had built, the contract was unanimously awarded to John Traff whose figure, including the extras , was about $6130 lower than his original base bid plus the extras.

July 15, 1948

Approved extras demanded by Village on Nixon project:

a) To separate sewage from ground water, requiring two more pumps

$1363

b) To provide emergency and exit lighting

$1473

August 19, 1948

Approved extra in amount of $653.75 for additional basement windows, install copper water bar on foundation and provide for future East basement door. All in East half of area under gym that at present is not to be floored. Also authorized extra of $662.40 for heat controls in west basement rooms as this had been omitted from specifications.

Approved first payment to John Traff -- $17,315.00.

October 21, 1948

Approved extra of $275 for construction of vault for Public Service equipment, plus cost of underground trench from Romilly hall for service, plus $425 to Public Service for cable.

November 18,1948

$50 added to above cost of cable plus service charge. $53 added to above cost of vault.

November 29, 1948

Approved splicing of 27 inch roof girders in gym as unable to get delivery of full length 62 foot 4 inch beams.

December 16, 1948

Splicing of above beams to be by riveting and subject to the approval of the structural engineer who worked on the original drawers.

January 20, 1949

See report of the Village inspection of Nixon Addition and request for an impartial report which is attached to the Minutes – Submitted by Robert W. Hunt Company.

February 17, 1949

Contract awarded to the American Bronze Company for $140 to supply a bronze plaque to be put in the new addition.

April 11, 1949

Approved installation of additional blackboards and cork boards in new basement shops and health room to make them suitable for classroom use at an extra of $900.00.


Compiled by:

Charles N. Field
Member of School Board
District 92 ½
1945 to 1949

The Nixon School in 1957

The Nixon School in 2002.

Last Modified:  10/08/2002